Hearing recommends new dike with gated culverts in Machias
The planning for the replacement of the Machias dike bridge achieved a milestone on September 30 with a public hearing to gather public input on the purpose and need, bridge alternatives and potential impacts from the alternatives. A dozen stakeholders offered comments...
The planning for the replacement of the Machias dike bridge achieved a milestone on September 30 with a public hearing to gather public input on the purpose and need, bridge alternatives and potential impacts from the alternatives. A dozen stakeholders offered comments during the meeting, with all of them recommending to replace the aging dike with a new dike with gated culverts designed to accommodate potential sea-level rise.
Marshfield Fire Chief Danny Bowker stressed the importance of the river for firefighting, which would be unavailable if it were sea water. No one spoke in opposition to an exact replica replacement, although past meetings have included comments from conservation and environmental organizations encouraging restoring seawater exchange to the Middle River.
The meeting, a requirement under the National Environmental Policy Act (NEPA) Environmental Impact Statement process, was attended by about 35 individuals, a much lower number than past meetings. Several speakers expressed frustration with the number of meetings over the years and stressed the intensive process followed by the Upper Machias Bay Master Plan (UMBMP) project, which identified an "in‑kind" dike as the preferred alternative.
Bowker commented, "You folks need to study and calculate the thousands of hours spent on that plan and in prior studies. The thousands of volunteer hours already spent on this represent a major investment."
Ian Gorecki from Maine Department of Transportation (MDOT) noted that the UMBMP report has been received as part of the formal record and will be considered; however, that plan procedure does not replace the process required by federal law for an Environmental Impact Statement (EIS). Hannah Rice, who chaired the UMBMP leadership team, acknowledged the extensive effort contributed by the community to the plan and the hope that the broader areas addressed in the master plan, including the risk of flooding in the town's downtown, would be able to complement the dike replacement.
During the hearing, Kimberly Nunlist of East Machias commented, "I have questions about the methods and results, and I am not yet convinced there is no connection between the dike structure and the downtown study." She added, "I ask that flooding be considered among possible environmental impacts, both in areas that already flood and areas that may newly flood under proposed downtown mitigation options, including the proposal for a sea gate. I hope we can continue to tackle these issues with collaboration and mutual respect."
That point was echoed by Karen Ortiz from Machiasport, who stated, "It's really important that we collaborate on how it's going to affect the whole of the river and the bay."
Anson Bergonzi of East Machias observed, "The dike has been the way that it is for over 100 years. The wildlife is established on the other side opposite the ocean, and it has become accustomed to that. I would hate to see it not replaced in‑kind with the dike and the trail and everything maintained as it is, but everything lifted up several feet to account for storms, seawater rises, any issues that come along with that."
Project studied for years
The initial dike was completed in 1868 and enlarged in 1890s to accommodate the railroad. The existing structure includes four timber box culverts with flap gates at the downstream end to prevent seawater incursion. The area behind the dike has moved from a salt marsh to a freshwater marsh with agricultural use of reclaimed lands. The former Machias landfill abuts the Middle River and was mentioned as a concern by several speakers for any of the alternatives.
The dike project began in 2009 when the MDOT initiated a bridge improvement project and hosted its first public meeting to discuss the bridge condition and introduce potential alternatives. While some spoke in favor of the possibility of restoration of saltwater flows and improved fish passage, solutions that would remove the flap gates and increase the extent of tidal inundation upstream of the causeway were a serious concern for upstream property owners because of potential flooding.
In 2015, MDOT completed a tidal hydraulic and alternatives analyses study to consider the effects of different structure types and opening sizes for tidal flows under existing conditions, fish passage, potential flooding of lands resulting from increased tidal exchange, and potential sea level rise (SLR) impacts. The 2015 hydraulic study concluded that only a fully gated culvert replacement would completely avoid increased flooding of lands. If a culvert alternative was modified to include some open culverts, it could improve fish passage and limit flooding. A bridge alternative would provide full tidal exchange but would result in substantial flooding of the land upstream of the dike.
In 2018, the MDOT initiated a bridge culvert replacement project and presented a fully gated replacement culvert alternative as the preferred alternative at a public meeting due to concerns for flooding the National Register eligible trotting park at the northeast corner of the project. This alternative was received favorably by meeting attendants; however, as preliminary design moved forward and time elapsed, three major factors changed that led to reevaluation and further study of bridge and culvert alternatives beginning in 2020.
The current structure is generally considered a barrier to fish passage. In June 2020, the National Oceanic and Atmospheric Administration (NOAA) expressed concerns that the replacement with a fully gated culvert option would further inhibit fish passage between the Middle River and Machias River, particularly for the endangered Atlantic salmon, suggesting that a fully gated culvert alternative may not meet the requirements of the Endangered Species Act.
Throughout the course of the hydraulic study and pre‑environmental evaluation effort, the MDOT considered a total of 21 alternatives, including variations of a fully gated replacement with culverts, partly gated replacement with culverts, rehabilitation of the existing structure and replacement with an at‑grade bridge span. In May 2022, the MDOT publicly announced that a bridge to replace the existing four box culverts was the preliminary preferred alternative. The decision to choose a bridge as the preferred alternative was mainly based on information received from the National Marine Fisheries Service (NMFS) regarding potential effects under the Endangered Species Act and information gained during the public involvement process.
In 2022 the MDOT and the Federal Highway Administration held a public meeting in Machias to discuss the preferred alternative. MDOT heard from numerous members of the public in opposition to a bridge, specifically those who would be impacted by restoring tidal exchange upstream of the dike and causeway. In response to the public comments, MDOT further investigated and analyzed the impacts of the bridge and culvert alternatives on the endangered Atlantic salmon, the National Register eligible Riverside Park trotting track, the landfill and property. Based on the additional analysis, In November of 2023 the preferred alternative changed from a bridge to a fully gated culvert replacement.
In 2024, a ruling by NOAA under the Endangered Species Act found that replacing the dike with a similar system of gated culverts would have significant impact on fish species of concern requiring a higher level of environmental review. The MDOT was required to restart its process and undertake a full environmental impact statement process, rather than a less stringent environmental assessment.
Next steps in the EIS development include creating a draft EIS with a target completion date of April 30, 2027, followed by a public meeting and comment period during June 2027. MDOT and the U.S. Army Corps of Engineers would submit permit applications for preferred alternatives during July 2027, and the final EIS and Notice of Decision would be posted to the Federal Register on October 10, 2027. Gorecki emphasized that the intent throughout the EIS process is intended to result in an EIS and record of decision that is "transparent and defensible."